A major part of the design brief was to ensure energy efficiency whilst addressing the workability of such a large facility

Storage King - 248 New Cleveland Road, Tingalpa, Queensland

SITE SPECIFICATION

Footprint: 2,762m2.  Levels: 3.  Net lettable space: 5,700m2.  120m2 of retail showroom, office and amenities. 80m2 of loading dock and hoist circulation area.

PROCESSES BY STEEL STORAGE

  • Site analyses
  • Facility design layout
  • Feasibility study
  • Town Planning co-ordination
  • Architectural Design
  • Development Approval
  • Engineering Design
  • Building Approval design
  • Consultant co-ordination
  • Construction budget
  • Quantity Surveyor reports
  • Turn key Project Management
  • Design and Construct
  • Internal high partitioning
  • Gloss White hallway panelling
  • Branding involvement  
 

SPECIAL FEATURES

To make the project feasible it was necessary to construct a facility with storage on 3 individual levels. Cutting into the existing terrain to achieve the 3 levels ensured that the structure remained below the statutory height guidelines.  
 
The building was designed in house by Steel Storage’s own design team. This ensured that the facility was laid out in the most ‘self storage’ efficient format whilst drawing on the many years of knowledge and experience of the construction of self storage facilities.
 
The major part of the design brief was to ensure Energy Efficiency whilst dealing with the ‘workability’ of such a large facility. This was achieved by various methods.
 
The ground floor level was encased in ‘split block’ to achieve not only an aesthetically pleasing finish but also to provide heightened insulation to the whole area. Further insulation and internal wall lining was applied to all other external wall surfaces to reduce radiant heat.
 
Whilst large rotary vents along with foil backed insulation were installed in the roof, no translucent sheeting was used to ensure reduction of radiant heat and also eliminating the ongoing maintenance/replacement of brittle sheets in the future.
 
Strategic placement of awnings along with energy efficient glass and insulated rear walls ensured that the ‘shopfront display’ areas had little effect on the ambient temperature within the facility.
 
Going to three levels took the Class of building into another category under the Building Code and therefore an ‘Alternate Design Solution’ was proposed. This entailed the installation of a full sprinkler system along with smoke detection and extract all linked directly to the Local Fire Brigade. Numerous design meetings were held with the Brigade to ensure full compliance not only with the Building Code and relevant Australian Standards but also the Queensland Fire & Rescue ‘Operational Requirements’
 
The internal partitioning was made up of the Steel Storage ‘Streamline’ interlocking SS750 zincalume dividing panels and the 500mm wide Gloss White Hallway panel complete with the plastic inserts to the bottom channel and all manufactured in-house at our manufacturing facility in Singapore.
 
Roller Doors and Swing doors throughout the facility were imported from our London manufacturing facility. The doors came complete with a unique ‘leather look’ plastisol surface finish all to the Storage King colours. The swing doors also incorporated the newly released recessed Steel Storage lock.
 
A number of the units were installed with the new revolutionary Steel Storage “Cubix’ stacking system enabling up to four times the net lettable area from the one space. This new system is providing higher yield which in turn means higher business value and increased income.
 
The whole project was topped off with an ultra modern retail area where point of sale furniture was manufactured specifically for this project by a bespoke joinery company all built in the Storage King specific corporate colours.
 