Steel Storage Group  •  Australasia  •  Europe  •  Asia  •  Middle East
Carrara Storage

Fort Knox Storage - Stage 1

  1. THE CLEAR SITE
  2. EARTHWORKS
  3. SOIL PROBLEMS
  4. UNDERGROUND SERVICES
  5. FORMWORK
  6. CRANE BROUGHT IN
  7. AMMENITIES
  8. MEZZANINE
  9. EXTERNAL ELEVATION
  10. CLOSE TO COMPLETION

Project Overview
Design & Construct
Turn Key Project Management

Client
Cantray Pty Ltd. (Garth Davidson)

Site Specs
Gross Block Area: 8391 m2
Gross Roof Area: 3908 m2
Site Cover: 46.33%
Driveway 2446 m2
Gross Floor Area: 3908 m2
Number of units: Undisclosed
Stages: 3

Processes handled by Steel Storage
Site analyses
Facility design layout
Feasibility study
Town Planning Co-ordination
Architectural Design
Development approval
Engineering Design
Building Approval Design
Consultant Co-ordination
Construction Budget
Quantity Surveyors reports
Turn key Project Management
Design & Construct
Internal high partitioning
Gloss white hallway panelling
Branding involvement

Special Features
Large double storage building with tilt panel fire separation wall, corridors with multiple egress via Fire doors through tilt panel

Learning experiences
Geotech reports don't always pick up problems with latent soil conditions


1. THE CLEAR SITE
The clear site with minimal fall and little stripping required prior to civil earthworks commencing.
BACK TO TOP (PHOTO)

2. EARTHWORKS
The earthworks have commenced and shown is one of the excavations for a besser block retaining wall which will be sealed and stormwater line installed to manage excess water and direct it to the stormwater system.
BACK TO TOP (PHOTO)

3. SOIL PROBLEMS
Excavation revealed some latent soil problems on this site, which Engineers are working on the options in a meeting between Consultants, Clients, Steel Storage Project managers and the Civil Contractors.
BACK TO TOP (PHOTO)

4. UNDERGROUND SERVICES
Once the soil conditions are resolved the job proceeded, underground services are installed and concrete road and ground slabs are well underway.
BACK TO TOP (PHOTO)

5. FORMWORK
Shown here is the formwork for the concrete tilt panels, which are all cast on site and then lifted into place by crawler crane. The panels are cast on top of each other up to approximately five at a time.
BACK TO TOP (PHOTO)

6. CRANE BROUGHT IN
With the form work stripped the precast panels are exposed and ready for the crane, once they are all cast the heavy lifting crane is brought in and they are usually all installed in a day.
BACK TO TOP (PHOTO)

7. AMMENITIES
This project as shown here has the complete office and residence area constructed from heavy concrete tilt panel construction, which when completed looks very effective.
BACK TO TOP (PHOTO)

8. MEZZANINE
Inside the main structure, visible is the new mezzanine floor and Steel Storage internal partitioning material on steel stillages ready to be unpacked and installed.
BACK TO TOP (PHOTO)

9. EXTERNAL ELEVATION
The external elevation showing detailing to the gutter, downpipes and single stage louvre vents and roller doors in a different colour to the wall cladding.
BACK TO TOP (PHOTO)

10. CLOSE TO COMPLETION
Almost project completion with signage in place and car park roadways and landscaping being finished off prior to handover and opening.
BACK TO TOP (PHOTO)